INVESTMENT NAME |
INVESTMENT TYPE |
PHASE |
Construction of water supply pipeline in Svetonedeljski breg - odvojak street |
construction |
completed |
Construction of water supply pipeline in Klenovec street in the area of Sveta Nedelja |
construction |
completed |
Construction of water supply pipeline in Stublov zdenac street in Mala Gorica settlement |
construction |
completed |
Construction of water supply pipeline in Habdelići street in Novaki settlement |
construction |
completed |
Construction of water supply pipeline in Rakitovec street in Orešje settlement |
construction |
preparation |
Construction of water supply pipeline and pumping station in Gaj street |
construction |
procurement |
Reconstruction of water supply pipeline in Videkovići, Loza and Novačka road (from Vojvodići to Rakitska road) |
construction |
in plan |
Construction of water supply pipeline in Braće Radić street |
construction |
in progress |
Construction of water supply pipeline in Zelengaj street |
construction |
in plan |
Construction of water supply pipeline in Borovina street |
construction |
in plan |
Construction of water supply pipeline in Miholići street |
construction |
in plan |
Construction of water supply pipeline in Poduzetnička street |
construction |
in plan |
Construction of water supply pipeline in Dekanići street - I. and II. branch |
construction |
in plan |
Construction of water supply pipeline in Kerestinečka road |
construction |
in plan |
Construction of water supply pipeline in Plohi street |
construction |
in plan |
Construction of water supply pipeline in branch of Srebrnjak street |
construction |
in plan |
Construction of water supply pipeline in Zagrebačka street |
construction |
in plan |
Construction of water supply pipeline in branch of Vojvodići street |
construction |
in plan |
Construction of water supply pipeline in Trnac street |
construction |
in plan |
Construction of water supply pipeline in Anina street |
construction |
in plan |
Construction of water supply pipeline and fecal sewage in Damira Horvatića and Rakajka streets |
construction |
completed |
Construction of water supply pipeline and fecal sewage in Petra Preradovića and Stanka Vraza streets |
construction |
completed |
Construction of fecal sewage in Ledine street |
construction |
in plan |
Construction of water supply pipeline and fecal sewage in branch of Selčica street |
construction |
in plan |
Construction of fecal sewage in Padež street |
construction |
in plan |
Construction of fecal sewage in Okićka street |
construction |
in plan |
Construction of fecal sewage in part of Dr. Franje Tuđmana street |
construction |
in plan |
Construction of fecal sewage in part of Topolje street |
construction |
in plan |
Construction of fecal sewage in RZ Novaki |
construction |
in plan |
Construction of main collector - GSK1 |
construction |
in plan |
Construction of fecal sewage collector and pumping station in Industrijska street odvojak I, Industrijska and obrtnička street in the area of Sveta Nedelja |
construction |
in plan |
Reconstruction of Rakitje pumping station |
projecting |
in plan |